Resource guide

AI Data Centers in Florida and the Law Governing Them

Florida's data center law sets utility-cost and water-permit rules, while the Fort Meade campus and Duke Energy's tariff remain unresolved.

Last updated November 16, 2026 1621-word guide By Jonathan West

What Florida's Data Center Law Requires

Florida's data center law requires large-load utility tariffs and restricts certain water permits. A Fort Meade report from WUSF, a Florida public radio station, describes a campus that remained a proposal as of November 16, 2026. A separate WUSF report on the tariff proposed by Duke Energy describes a dispute before the Florida Public Service Commission with no decision found.

The Florida Senate's bill page identifies the measure as CS/CS/SB 484 (committee substitute for committee substitute for Senate Bill 484), Data Centers. It became Chapter 2026-65 and took effect July 1, 2026, except as otherwise provided. The Senate's abstract says local governments retain authority over comprehensive planning and land development regulations relating to large-load customers. It also requires public utilities to provide minimum tariff and service provisions for those customers.

The finer requirements below come from the enrolled bill text. Section 3, which creates s. 366.043, defines a large-load customer by an anticipated monthly peak of at least 50 megawatts at one location. Customers cannot split a load to escape that classification. The threshold concerns expected electricity demand, so a proposed campus's floor area alone does not establish whether it qualifies.

Under s. 366.043, tariffs must ensure each qualifying customer bears its full cost of service without shifting that cost to the general body of ratepayers. Utilities were required to file compliant tariffs by October 1, 2026. Filing one and having it accepted as compliant are separate events. The reported Duke Energy dispute shows why that distinction matters.

The Senate abstract also describes a restriction on consumptive-use water permits for large-scale data centers. Section 5, which amends s. 373.262, requires a hearing before an application can be approved. For applications involving at least 100,000 gallons per day, it calls for water-use accounting and a conservation plan. It also requires reclaimed water where feasible. Those requirements matter at Fort Meade because WUSF reported that the proposal still needed water-use authorization.

Finally, the Senate abstract directs the Office of Program Policy Analysis and Government Accountability (OPPAGA) to contract for a study of large-scale data centers. Section 7 of the enrolled text sets a July 1, 2027 delivery date and covers economic and tax effects, land and water use, energy costs and rates, and public health and safety. The study is a future information source, not a permit for a campus.

Proposed Campuses

Stonebridge's Fort Meade campus had a city development agreement but remained a proposal, according to WUSF's April 22, 2026 report. WUSF, carrying reporting by Cindy Glover of LkldNow, described a proposed 4.4-million-square-foot data center on about 1,300 acres in northwest Fort Meade. The site is former phosphate mining land used for cattle grazing. WUSF reported an estimated project cost of $2.6 billion.

Fort Meade city commissioners voted to approve a 20-year development agreement in mid-April 2026, WUSF reported. That vote approved a development agreement, but it does not establish that construction is complete or that water use is authorized. WUSF reported that Stonebridge still needed multiple state and federal permits, including water-use authorization.

Water estimates need the same care as project status. WUSF reported projected potable-water use of about 50,000 gallons per day from the Upper Floridan Aquifer. WUSF also reported that early talks had projected 140,000 gallons per day. In an April 2026 letter sent the day after the city vote, Commerce Secretary J. Alex Kelly wrote that the projected water demand "appears woefully underestimated." Neither reported figure is measured operating consumption, because the campus remained a proposal.

WUSF reported a projected power need of about 1.2 gigawatts. The Southwest Florida Water Management District told WUSF that Fort Meade's existing water permit could not be used for the project. The development agreement, projected power need and outstanding water-use authorization describe different aspects of the proposal. None should be presented as evidence that the campus was operating.

The project list here stops at Fort Meade. Pasco County and Lakeland also appear in WUSF's reporting, but the cited pages do not give a verified status for those places. It does not establish that Fort Meade is the only proposal in Florida, or provide a verified location and status for every proposed campus. For the practical effects of living near a facility, see living near a data center.

Who Pays for the Power

Florida's enrolled bill text requires tariffs designed to make each large-load customer pay its full cost of service without shifting that cost to other ratepayers. It allows the commission to approve tools including construction contributions, demand charges, financial guarantees, minimum load factors and take-or-pay provisions. The text also says tariffs cannot hinder curtailing service when grid stability or public safety requires it.

Those are requirements and permitted tariff tools, not a finding that a particular utility filing passes review. WUSF reported on June 12, 2026 that Duke Energy withdrew its first data center tariff after the Legislature passed SB 484. According to the Florida Office of Public Counsel, Duke filed a second tariff that it intended to meet the law, placing data centers under large-load tariffs it had used for the past two years. WUSF reported that Duke did not respond to a request for comment.

The Office of Public Counsel disagreed. WUSF reported that the office said Duke's second tariff "doesn't comply with the new law" and filed a joint motion to dismiss. Public Counsel said Duke relies on a settlement agreement that it says protects customers from rate increases until January 1, 2028. The Office of Public Counsel argued that the statute protects customers both now and in the future. The commission must decide whether the tariff complies. No final decision was found.

The settlement argument about rates through January 1, 2028 therefore does not resolve the Office of Public Counsel's objection. Nor does the objection, by itself, establish that Duke's tariff will shift costs. WUSF's report presents Public Counsel's account of the two positions and leaves the compliance decision with the commission. For the wider bill question, see do data centers raise electric bills.

What the Law Says About Secrecy

Florida law already lets an economic development agency keep a company's site-selection plans confidential for 12 months after a written request and before an incentive agreement is signed. The enrolled bill adds no new confidentiality power for local governments. Under s. 288.075, as amended by Section 2, the additional extension of up to 12 months does not apply to data center information.

That caps the confidentiality route for a proposed data center at the initial 12 months. The provision should not be stretched into a promise that every project detail is public at once. Neither period covers every project record, and the enrolled text sets no release date for every document connected to a proposal.

WUSF reported a Fort Meade city vote on a development agreement while separately reporting that water-use authorization was still needed. If a campus is proposed nearby, separate the local land-development decision from the outstanding permit decisions. The guide to how to find out early about a data center covers the next steps for tracking a local proposal.

Facilities and Projects Tracked

This tracker separates an enacted law, a disputed tariff, a proposed campus and a study due July 1, 2027. A law's effective date is not a campus opening date.

ItemStatus as of November 16, 2026What the source saysSource
CS/CS/SB 484Law, effective July 1, 2026, except as otherwise providedChapter 2026-65 sets large-load tariff and service requirements and addresses water permits and a data center study.Florida Senate bill page
Duke Energy proposed tariffContested, with no final commission decision foundDuke filed a revised tariff intended to comply. Public Counsel says it does not.WUSF, June 12, 2026
Stonebridge Fort Meade campusProposal with a city development agreement, not builtWUSF reports that the project still needs multiple permits, including water-use authorization.WUSF, April 22, 2026
OPPAGA studyDelivery due July 1, 2027, under the enrolled textThe study is to address construction and operation of large-scale data centers, including costs, water and land use.Florida Senate enrolled bill text

The AI data center map is a separate way to look for locations. This table makes a narrower claim: it includes only the Florida items supported by the Senate record and the WUSF reports above.

Our Takeaway

Florida electric customers have a statutory cost-protection requirement, but they do not yet have a reported final ruling on Duke Energy's contested tariff as of November 16, 2026, according to WUSF. Residents near Fort Meade have a city-approved development agreement to examine, while WUSF reported that the proposed campus still needed water-use authorization. The enrolled bill text keeps the initial 12-month confidentiality period for company site-selection plans but ends the additional extension for data center information.

This account does not serve someone who needs a complete inventory of Florida campuses or a prediction of Duke's eventual rates. The project reporting here covers Fort Meade, and WUSF reports a tariff dispute rather than its outcome. For either question, distinguish a proposed site's recorded approvals from its outstanding permits, and a utility's filed tariff from a commission decision.

What Would Change Our Answer

A commission ruling on Duke Energy's tariff would resolve the compliance question WUSF reported as unsettled. A grant or denial of Fort Meade's water-use authorization would change the permit status WUSF reported as outstanding. Cancellation of the campus would end its status as an active proposal. None of those later outcomes is established by the cited reports.

Open the Florida Senate's enrolled SB 484 text, then compare its tariff and water-permit provisions with the dated Duke tariff report or Fort Meade report relevant to your location.

Frequently asked questions

▸ What AI data centers are planned in Florida?
The Fort Meade campus proposed by Stonebridge is the project supported by the WUSF reporting cited here. WUSF reported a city-approved development agreement, but the campus had not been built and still needed state water-use authorization. WUSF's pages also link Pasco County and Lakeland reports, and this is not a complete inventory of Florida proposals.
▸ What does Florida's data center law require?
Florida's Senate Bill 484 (CS/CS/SB 484) requires minimum utility tariff and service provisions for large-load customers, preserves local planning authority, restricts certain water permits for large-scale data centers, and orders a state study. The enrolled text also describes tariffs intended to keep each large-load customer's full service costs from shifting to other ratepayers. The law took effect July 1, 2026, except as otherwise provided.
▸ Will Florida residents pay for data center electricity upgrades?
The law requires tariffs designed to keep a large-load customer's full cost of service off other ratepayers. That requirement does not settle whether Duke Energy's proposed tariff complies. WUSF reported the Office of Public Counsel's objection, and no Public Service Commission decision was found.
▸ Is the Fort Meade data center approved?
Fort Meade approved a development agreement, according to WUSF, but that is not approval to build and operate the entire campus. WUSF reported that the proposal still needed multiple state and federal permits, including water-use authorization, and it remained a proposal.
▸ Can Florida keep a proposed data center secret for 12 months?
Partly. Florida law already lets an economic development agency keep a company's site-selection plans confidential for 12 months after a written request and before an incentive agreement is signed. Senate Bill 484 ends the additional extension of up to 12 months for data center information, so that route is capped at 12 months. Neither period covers every project record.